Penn Medicine Pharmacy

Project Type
Institutional / Healthcare
Services Provided
Basis of design support, with Jim O'Donnell working to establish TMI Climate Solutions as basis of design Custom air handling unit supplied by TMI Climate Solutions Collaboration with WSP Philadelphia, the project's consulting engineer
Description

The Hospital of the University of Pennsylvania (Penn Medicine) Pharmacy Relocation project required an air handling solution that could meet the demanding air quality, reliability, and maintenance requirements of a healthcare environment.

Unit Configuration

  • 47,500 CFM capacity
  • 8-module construction, approximately 56,000 lbs operating weight
  • Full walk-in service vestibule and dedicated heater service vestibule for enhanced maintenance access

Thermal Performance and Construction

  • Chilled water cooling and hot water heating
  • 4″ closed-cell polyurethane foam insulated walls with no-through-metal construction
  • 12″ aluminum base with 3″ closed-cell polyurethane foam insulated floor, also no-through-metal
  • 2″ rolled-lip welded floor with integrated drains for wash-down capability
  • Aluminum interior and exterior liners with an air-dried enamel exterior finish
  • 304 stainless steel liners in all wet sections

Airflow and Controls

  • Six-fan supply array and six-fan return array, each fan with an independent ABB ACH580 NEMA 12 ULH variable frequency drive (12 VFDs total)
  • Channel blender assembly
  • Two Paragon MTSE airflow measuring stations with independent supply, return, and outside air measurement

Filtration and Indoor Air Quality

  • MERV 8 prefilters, MERV 11 intermediate filters, and MERV 14 final filters
  • Cooling coil UV light system for coil cleanliness and biological growth control

Humidification

  • Carel adiabatic humidification system with integral pump station in the service vestibule
  • Mist eliminator section for moisture carryover protection
5
3
2